Case Study
After three decades of dependable performance, it was time to upgrade the 12.5kVA Erskine AC Industrial UPS installed at a remote gas field in Pakistan to ensure continued protection of critical infrastructure.
The client required a like-for-like replacement that could integrate smoothly with existing systems while offering improved efficiency and longevity.
Dale Power Solutions supplied a 15kVA Erskine Industrial UPS as a direct engineered replacement. Featuring open protocol technology, the new system allowed the client’s technical team to carry out commissioning independently, reducing implementation time and costs.
Despite early challenges due to Covid-related global delays, the project was delivered and commissioned on schedule. The UPS system was successfully transported, installed, and fitted with a new battery temperature sensor to optimise performance and battery life.
Cost-Efficient: The project was delivered under budget.
Timely Execution: Installation and commissioning were completed on time.
Future-Proof Reliability: The new Erskine UPS is designed to deliver 20+ years of dependable service in demanding industrial environments.